W003334: G J Crookes Hospital : Extend Staff Residences.

Contractor: JJS Construction cc
Project Leader: Hans Ramadhin

 

The site was handed over to the Contractor on the 29/05/2009 with a contract period of 13 months and an estimated First Delivery of 29/06/2010. The Total Contract Value is R 6 621 929.82


The Contractor’s workmanship is satisfactory and the project is currently ahead of programme and is estimated to be complete within the contract period of 13 months. The Client Department, Consultant and Project Leader are all satisfied with the progress being made on site.