W030404: Department Of Health : Phateni Clinic : New Clinic.

Contractor: Zethembe Maintenance and General Services
Project Leader: Hans Ramadhin

 

The site was handed over to the Contractor on the 30/07/2009 with a contract period of 14 months and an expected First Delivery date of 30/09/2010. The Total Contract Value is R 9 218 769.00.


The contractor is a previously disadvantaged woman. Her workmanship is above standard and the project is currently on programme and is estimated to be completed within the contract period of 14 months. The Consultant and Project Leader are satisfied with the progress being made on site.