Project Name |
Ohlalwini School |
Project Location |
Umkhanyakude Distrcit Municipality |
Project Amount |
R 9 147 500.09 |
Start Date |
08 July 2009 |
Completion Date |
The project completion date is 10/09/2010 |
Contractor |
Contractor Name : Mthokozisi Building Construction cc |
Background |
The school has been earmarked for the community of ohlalwini after looking at the distance traveled by learners attending at Singose, Othobothini and Endabeni local school which are
The project is 60% complete; electricity & Water have been installed but not connected. |
0rganisational Arrangements |
|
Project Status |
|
Work Undertaken |
The project scope involves construction of new 12 classrooms ,5 laboratories , 1 media c |
Innovativeness of the project |
The project is not necessarily EPWP defined but the elements are instilled through the employment of local labourers. The employees have been trained on Occupational Health and Safety (OHS), HIV/AIDS and steel reinforcing. |
NYS Placement |
2 NYS learners’ phase 2, bricklaying & plastering have been extended practical training to March 2010. |
Impact on the Community |
Established (PSC) has intensified the hiring of unemployed local laborers with the aim of alleviating poverty and skill transfer’s objective. Electrical work will be subcontracted. |
Classrooms structure under construction |
|
Learners receiving concrete from the mixer |